When to book each stage inspection on a Werribee build

How to time slab, frame, lock-up and the rest so nothing is covered before it is checked.

Werribee 3030 · 22 January 2026

In short: Every stage has a short window between being finished and being hidden. Booking well means knowing what closes each window.

The window is set by the next trade

A slab can be checked only until the concrete truck arrives. A frame can be checked only until the insulation and plaster go on. On a busy Werribee estate those gaps can shrink to a day or two, so the trigger for booking is the next trade's date, not the end of the current one.

Ask for dates early

Supervisors usually know the pour date or the plaster delivery a few days ahead. Ask for it as soon as the previous stage starts and pass it to us. A booking we can plan is far easier than one made the afternoon before.

Slab: the day before the pour

Pods, steel, chairs and the vapour barrier all have to be in place. Earlier than that and the work is incomplete; later and it is under concrete.

Frame and lock-up: before anything covers the studs

The frame inspection needs the roof covering on but no sarking or insulation hiding the members. Lock-up follows once windows and doors are in, before plasterboard is delivered.

Fixing, waterproofing and handover

Waterproofing is checked after the membrane cures and before tiling. Fixing comes before the painter. Pre-handover is about a week before the keys, so the builder has time to act on the list.

If you can only afford a few

Choose slab pre-pour, frame and pre-handover. The first two are the only times structure can be seen, and the last is your final chance to have items fixed at the builder's cost.

Written by our local inspection team from work carried out in Werribee. Licensed building practitioners, Building & Plumbing Commission registration CDB-U 53425.

Guides

More new construction stage inspections guides for Werribee

All guides →

Book a building inspection in Werribee

Instant online pricing, or talk to the booking team on 1300 471 805.

FAQ

Questions Werribee owners ask about this

Can I book all the stages at once?

Yes. We hold the series and confirm each visit as the supervisor gives dates.

What if the builder does not tell me the dates?

Ask in writing for notice of each stage. Your contract usually entitles you to progress information.

Do you need me on site?

No, but you are welcome. We arrange access with you or the supervisor.

What happens if a stage is already covered?

We inspect what remains visible and say clearly in the report what could not be seen.

CallGet a Free Quote