The last inspection before practical completion, while the builder is still responsible for putting things right at no cost to you.
One of our inspectors will call you back. If it is urgent, call 1300 471 805.
Werribee handovers have turned up leaking showers, exhaust fans blowing into the roof, rainheads with overflow slots that are no longer allowed and wall cappings screwed through their tops. These are function items, not cosmetic ones.


Annotated findings from Pre-handover (PCI) inspections.




1Bored piersAfter the holes are drilled and the cages set, before concrete goes in
2Slab pre-pourOnce pods, steel and membrane are down, the day before concrete
3FrameWhen walls, trusses and roof cover are up, before any sarking or insulation hides them
4Lock-up (pre-plaster)With roof, windows, external doors and cladding on, before plasterboard
5FixingWhen doors, skirtings and cabinetry are in, ahead of the painter
6WaterproofingAfter the membrane has cured and before the tiler arrivesInstant online pricing, or talk to the booking team on 1300 471 805.
The same day. Your position is strongest before you sign off at practical completion and before final payment.
Yes, to watch how water drains and whether anything leaks. We do not pressure test or certify the plumbing.
Overflow slots on box gutter rainheads are no longer accepted; an open weir or an approved alternative is required so water spills away safely.
No. The occupancy permit is issued by your building surveyor. Our report deals with the condition of the house.
Yes, where it can be reached safely or viewed by drone. Roof cappings and flashings are a common handover item in Werribee.
Yes. A reinspection confirms which items are closed before you take possession.